Tagoloan Substation


Project: 2x150 MVA; 138 kV / 69 kV Tagoloan Substation
Client: Cagayan Electric Power and Light Company, Inc. (CEPALCO)



The Cagayan Electric Power and Light Company (CEPALCO) has contracted Meralco Industrial Engineering Services Corporation (MIESCOR) to undertake the Engineering, Procurement, Construction and Commissioning (EPCC) of its 138 kV/69 kV Substation in Tagoloan, Misamis Oriental with two (2) 150 MVA power transformers.
The Scope of Work for this component of the EPCC contract includes the detailed design, manufacturing, supply, delivery, erection, installation, system integration and testing and commissioning of the 138/69kV Substation, plus associated telecommunication and protection facilities.
The project is expected to take 427 Calendar days. By June 30, 2015 the substation is expected to be capable of transmitting back-feed power supply and completed by July 31, 2015.